TLBI CIRCUITs:
In This lesson we will be learning about TLBI circuits.
In This lesson we will be learning about TLBI circuits.
- NORMAL POSITION
- DISPATCHING TRAIN
- TRAIN ENTERING INTO BLOCK SECTION- AUTO TRAIN ON LINE CODE TRANSMISSION.
- TRAIN ARRIVAL
- NORMALIZING OF BLOCK SECTION
- NORMAL LC CANCELLATION
- PUSHBACK LC CANCELLATION
- TELEPHONE CIRCUIT
- SPECIAL CIRCUIT ARRANGEMENT
1.NORMAL POSITION
- Normally Block handle is at Line Closed Position
- SM key - IN
- SH key -IN
- S1(Normal Cancellation) and S2(Push Back Cancellation) - Normal Position
- TOL and Time release indication - White
- Galvometer- Zero current position.
- All the relay except 1R and 1TPR are in de-energized condition
2. DISPATCHING TRAIN - Part 1
- Bell code transmission to give CALL ATTENTION from station A to Station B
Step 1: PB1 Button is Pressed(At Station A) , Negation On Line , BLR picks up and sounds the bell (At Station B)
Step 2: PB1 Button is Pressed(At Station B) , Negation On Line , BLR picks up and sounds the bell (At Station A)
Step 3: Verbal Communication for grant of Line Clear take place between SM of station A and Station B over Block Telephone.
Step 4: For Sending a train from Station A to Station B
- TCF code transmission from Station A to Station B
- PB1 and PB2 Pressed simultaneously (At Station A)
- PBPR picks up proving 1R up (At station A)
- Positive On Line (+ve On L1 and -ve on L2)
- Galvo Deflects, NR picks up and bell sounds(At Station B)
- With PBPR up power is connected to transmitter.(At Station A)
- The Modulating frequency F1(85 Hz) is selected as loop between F1
and C is completed by Handle 'N' contact is the transmitter.(At STN A)
- FM Code 'F1' on Line
- Input Circuit to receiver of same station is isolated by PBPR back
contacts. (At STN A)
- On Getting the Bell and Galvo deflection at STN B, SM Turns the block
Handle as far as Y Point. Further rotation is Not Possible as the handle
is in locked position.(At STN B)
is in locked position.(At STN B)
- At Station B
- Feed to receiver is connected through DY contact,
- CR1 picks up at station B on receipt of modulating current F1
by receiver.
- Lock Magnet picks up at Y to release the Block handle and Now
turned to right position('Train coming From' position)
- While the Block Handle is being turned from Normal Position to R
Position, The circuit controller contact (XY-RD-LB) of the handle in the
line circuit , in series with the relay NR is opened between the Y and
D points.(At STN B)
- On Opening circuit controller contact in Line circuit, the resistance R3
in parallel to 'XY-RD-LB' and in series to line circuit results in reduction
in the volume of the line current (which is greater than the line drop
away current of NR).This cause a click on Galvo needle at both stations
,from this click SM of button pressing station comes to know that the
block handle at other station has been turned.(At STN B).
- Knowing Block Handle has been turned from the click on the Galvo
needle , PB1 and PB2 at station A are released.